What happening at section 5 and 6: Hirwaun junction (Hirwaun road/Brecon road/A465 roundabout)

  • archaeological investigations
  • demolishing existing properties
  • laying temporary road
  • building bridges
  • installing drainage and culverts
  • moving utilities
  • building a roundabout

To build this road, we will cut up to 40 feet (12.5 metres) into the surface.

We will build a bridge built over the A465 to provide access to the Mynydd Bwllfa wind farm.

We will build a roundabout at Trewaun to connect Penywaun and Hirwaun. We will build 2 bridges to connect Brecon road to the A465.

We will build a temporary road to provide space for the new road. There will be no access to the A465 at the new Hirwaun Junction.

Current progress

We have:

  • cleared vegetation and site to prepare for construction.
  • undertaken archaeological investigation next to the windfarm access road.
  • diverted utilities to move services from the construction area.
  • demolished building within the scheme area.
  • constructed new Hirwaun West Bridge substructure, erected precast concrete beams for bridge deck construction.
  • constructed new temporary highway to create space to build the Hirwaun East bridge.
  • diverted traffic onto temporary roundabout to allow for bridge construction.
  • installed new drainage culvert under Hirwaun Road.
  • commenced construction of the Hirwaun East bridge.
  • temporary road opened on A465 to create space to build Trewaun retaining walls.
Works at Trewaun
Works at Trewaun

Next steps

  • constructing a retaining wall next to the houses in Trewaun.
  • extending the temporary road from Tramway to a new temporary roundabout to be located to the west of the current layout at the Hirwaun (Trewaun) junction.
  • relocating the temporary roundabout at Hirwaun (Trewaun) to a new location further east at Windfarm Road.
  • commence construction of new westbound A465 carriageway between Vale of Neath and Hirwaun. 
  • ongoing work to construct Hirwaun East overbridge that will connect Brecon Road to Hirwaun Road (A4059).

For traffic news on this junction, visit Traffic Wales.

First published

15 September 2021

Last updated

23 February 2023

Part of

Spread the love
Team @ AberdareOnline

Team @ AberdareOnline

Leave a Reply

Your email address will not be published. Required fields are marked *